Mill Creek Tunnel Project Update

Southland/Mole Joint Venture has completed excavation of 7 shafts and with 1 shaft remaining ranging from 22’ to 35’ diameter and 110’ to 190’ deep for the Mill Creek/Peaks Branch/State Thomas Drainage Relief Tunnel Project. There are a total of 8 shafts on the project (5 Intake Shafts, 1 Outfall Shaft, 1 Dewatering Station Shaft, and 1 Access Shaft).

Crews are currently mining with a 32’-6” diameter TBM, (3,000 lf remaining). 23,000 LF of tunnel excavation has been completed with Main Beam TBM (10,000 lf at 37’7” and 13,000 lf at 32’-6”). The JV is currently mobilizing equipment for cast-in-place tunnel concrete lining operation.

In addition to the shafts and mainline tunnel, this $206 million project for the City of Dallas includes 6 lateral tunnels excavated by roadheader or excavators/breakers and a dewatering station. The ground is primarily Austin chalk. There are 6 working sites within city environment and tunneling under city infrastructure (including state highways, light rail tunnels/surface tracks, rail roads).

The estimated date of completion is March 04, 2023.

Owner: City of Dallas; Lead Designer: HALFF; Tunnel Designer: COWI; CM: Black and Veatch; TBM Manufacturer: The Robbins Company; Contractor: Southland Mole JV (Southland Contracting & Mole Constructors); Subcontractor: Oscar Renda Contracting, Inc.; Contractor Design Engineer: Aldea Services.

Personnel: SMJV Operations Manager: Kent Vest; SMJV Senior Project Manager: Quang D. Tran, P.E.; SMJV Project Manager: Nick Jencopale; SMJV QC Manager: Matt Jackson; SMJV General Superintendent: Mike Clingon; SMJV Senior Project Engineer: Jose Ortiz, P.E.; SMJV Field Engineers: Jason Lipp/Kade Conner.

Comments are closed here.

TBM: Tunnel Business Magazine's Weekly Newsletter and More

Get industry news updates and product information to help you stay up to date.

By submitting this form, you acknowledge that we may use your personal information for marketing communications.