McNally Construction Inc.

This $71 million project for the Region of Peel was issued NTP on June 6, 2013, with a scheduled completion date of June 30, 2016. The job consists of 9,775 m (6 miles) of 2,400-mm (94.5-in.) diameter trunk sanitary sewer to be constructed by tunneling through rock up to 51 m deep.  Additionally, 542 m of 400-mm (15.7-in.) diameter watermain is to be constructed. The caisson wall is completed for the launch shaft and excavation is under way.

Engineering consultants included Genivar (Design/Construction Manager), Golder Associates (Geotechnical Consultant), HC Matcon (Shoring), and Dufferin (Structural Concrete). Key Project Personnel include: Ajay Puri (Region of Peel), Chad Stephen (Genivar) and Jeff Reid (McNally Construction).

Share Article:

Comments are closed here.

TBM: Tunnel Business Magazine's Weekly Newsletter and More

Get industry news updates and product information to help you stay up to date.

By submitting this form, you acknowledge that we may use your personal information for marketing communications.