Hard Rock TBM Takes Tunneling to the Next Level in Norway
With compressive strength of up to 300 megapascals, Scandinavian rock is regarded worldwide as the ultimate test of mechanized tunneling technology. Among the leaders in hard rock tunneling, Herrenknecht rock TBMs have excavated around 820 km of tunnels in more than 200 projects since the year 2000. In late August the breakthrough of the Ulriken Tunnel for the expansion of the Norwegian railway network added another hard rock highlight to the list.
The railway tunnel through the Ulriken mountain is the first major traffic project in Norway to be realized with a Gripper TBM. On the west coast of Norway, the hard rock machine “Ulrikke” (Ø 9,300 mm) has bitten its way through extremely tough rock meter by meter in recent months. The miners of the Skanska Strabag Ulriken ANS joint venture have driven the 6.9-km long tunnel between the cities of Bergen and Arna with excellent top advance rates of up to 170 m per week.
RELATED: Skanska-Strabag Breaks Through on Ulriken Tunnel
In Norway, drill-blast tunneling traditionally dominates. “The realization that mechanical tunneling is a real alternative even in the extremely hard rock now seems to be spreading in Scandinavia,” says Eric Fourchault, Project Manager at Herrenknecht. Compared to traditional drill-blast, mechanized tunneling has a number of advantages. It has less impact on the mountain and provides highest safety for the crew, without the shocks of blasting. The short distance of only 30 m from the existing operational railway tunnel was therefore decisive for the use of a TBM at the Ulriken Tunnel. Furthermore, machine technology can achieve higher average advance rates, especially over long distances.
TBMs are already being preferred over the traditional drill-blast method in other Norwegian tunnel projects. For Norway’s latest large-scale infrastructure project, the Follo Line in Oslo, four Double Shield TBMs (Ø 9,900 mm) from Herrenknecht are creating the country’s longest railway tunnel. In 15 months of excavation, more than 19 km of the approximately 38-km long total route have meanwhile been driven as a tunnel.
RELATED: Hydro Project Marks Return of TBMs to Norway