Herrenknecht MTBM Secures Power Supply in West Africa
In late July 2017, Coleman Microtunnelling, a subsidiary of Bothar Group Australia, successfully completed tunneling for two power plant cooling water lines in Ghana with a Herrenknecht utility tunneling machine. The new oil-gas power plant puts the supply of electricity for people and business for the country on the West African Atlantic coast on a more solid foundation.
The 2,700 GWh per year capacity of the new Kpone Independent Power Plant (KIPP) is enough to reliably supply approximately 1 million households with electricity. In the operation of the oil-gas power plant located about 25 km east of the Ghanaian capital Accra directly on the coast, it will be cooled with sea water from the Atlantic Ocean via two cooling water lines.
For the construction of these underground sea water intake and outfall tunnels (2 m ID) Coleman Microtunnelling ordered a Herrenknecht AVND2000AB utility tunneling machine. Herrenknecht specially designed the tunnel boring machine with a salvage module for this special application: In the sea-outfall method pipelines are constructed from the coastline into the open sea. There, the machine has to be recovered under water. The salvage module prevents the machine and the tunnel from flooding. In addition, for cutter tool changes under high groundwater pressure, Herrenknecht equipped the machine (2.5 m OD) with a hyperbaric chamber.
RELATED: Herrenknecht Welcomes New Class of Apprentices
Two shafts on the coast served as starting point for the jobsite crew and the Herrenknecht AVND for a total of four pipe jacking drives between May and July 2017. In total, they covered a distance of 2,530 m. First, the tunneling specialists of Coleman Microtunnelling produced two tunnels from the two shafts toward the power plant. These 545- and 520-m long tunnels run under the mainland and connect the sea-outfalls and the power plant. Afterward, construction of the challenging tunnel sections under the sea floor started. Initially, the machine excavated a 1,085-m long tunnel from the coast to the target spot on the seabed for the extraction of the cooling water (“sea-intake”). There, the TBM was recovered by the jobsite crew at a depth of 17 m. Finally, the machine created a parallel 380-m long tunnel toward the sea which will later take the cooling water back into the Atlantic (“sea-outfall”).
Brent Jones, Project Manager for Coleman Microtunnelling, was impressed with the Herrenknecht support in Schwanau and the Herrenknecht service team responsible for the region: “We could not have done it without this extraordinary support. All through Christmas the supply of spare and wear parts went smoothly.”
Swen Weiner, Area Sales Executive Middle East for the Herrenknecht Business Unit Utility Tunneling, added: “The good project performance for the long sea-outfall drive in Kpone will be a benchmark for the future in the region.”