East Side Access Project Passes Major Milestone as Blasting Concludes Under Grand Central Terminal

The Metropolitan Transportation Authority (MTA) announced April 9 that sandhogs working on the East Side Access megaproject have concluded major blasting under Grand Central Terminal, where they are building two enormous caverns 160 ft below street level that will house eight tracks for Long Island Rail Road trains.

Since March 7, 2007, nearly 1,000 employees working 24 hours a day, five days a week, have completed more than 2,400 controlled blasts – all without affecting the nearby operations of MTA Metro-North Railroad or the New York City Subway. Approximately 857,000 cu yd of rocky muck were excavated and removed, enough to cover the entirety of Central Park 1 ft deep.

“This is a very significant milestone for the East Side Access project,” said Dr. Michael Horodniceanu, President of MTA Capital Construction. “The caverns are essentially now fully excavated. Much work remains to be done to build the platforms and tracks, and finish what is currently raw, cave-like space. But we now have a fully built shell in which all future work will take place.”

Each blast was overseen by an FDNY-licensed blaster. To conduct a blast, teams of sandhogs drill hundreds of holes measuring 1.5-in. in diameter into the mica-inflected granite schist that forms the bedrock of Midtown Manhattan. Together, the holes are loaded with 200 to 500 lbs of an explosive powder known as Emulex. After the sandhogs clear into a safe area, the Blaster-in-Charge issues a warning – “fire in the hole!” – and triggers the blast.

A short video of sandhogs conducting one of the last blasts for East Side Access’ Manhattan caverns can be found on the MTA’s YouTube channel, here: http://youtu.be/ms0nDGDrNc8

The contractors, a joint venture of Dragados USA Inc., and Judlau Contracting Inc., are continuing to perform miscellaneous concrete work until their contract is complete in June. They expect that they may need to make additional small blasts that will trim out pieces of rock in the cavern.

In addition to the blasting, the caverns under Grand Central have been excavated in part by two 200-ton TBMs that operated from September 2007 until June 2011, chewing through a total of more than 32,000 lf of Manhattan bedrock from 63rd Street to 37th Street.

Comments are closed here.