Herrenknecht Completes Final Double Breakthrough at the Emscher Sewer in Germany
With the breakthrough of the last two tunnel boring machines into the target pit in Oberhausen-Biefang on June 12, 2017, the tunnel and pipe jacking work for the Emscher sewer has been completed. Over a period of 25 years numerous, Herrenknecht tunneling machines and a wide range of additional equipment were successfully used in the Europe-wide unique environmental and sewage project of Emschergenossenschaft.
With the breakthrough of the two 10-km long main collectors of construction section 40 in Oberhausen, the tunneling work for the construction of the Emscher sewer has been successfully completed. Between October 2014 and June 2017, the two EPB Shields (Ø 3,397 mm) used by construction company PORR, achieved genuine peak performances with the support of Herrenknecht service experts. Thanks to their strong teamwork, the site crews were able to keep the average machine availability above 95% over the entire tunneling period. The result was outstanding top performances of up to 177 m per week and up to 582 m per month, which played a decisive part in the success of the overall project.
The two EPB Shields were the only machines in the entire project using the segmental lining method. With an inside diameter of 2.6 m, the twin tubes are among the smallest segmentally lined tunnels in the world. The entire tunneling system with a length of around 85 m was designed to be accordingly compact. The logistics were also adapted for the small diameter. Thus, for example, a muck removal concept with a locomotive was used, where excavated material was transported in buckets to the shaft and the finished segments were transported to the tunnel face.
RELATED: Herrenknecht TBMs Tunneling Under LA
One of the special tasks in the realization of construction section 40 was the technically demanding tunnel alignment with several, partially tight curve radii of up to 200 m. The alignment runs mostly below the A2 motorway and a multitude of inner city supply lines. In addition, an approximately 300-m long geological fault zone with sandy and groundwater-bearing subsoil had to be passed through. The limited space available at the total of three launch shafts necessitated an optimal logistics concept.
For these requirements, solutions were developed in advance and successfully implemented by the site crew during the construction phase.
Work on the overall Emscher conversion project began back in 1992, covering more than 400 km of new underground sewer tunnels. The inhomogeneous ground, the pipe position in up to 40 m depth, the long pipe jacking distances, the partially complex logistics and the wide range of different construction situations posed particular challenges in the creation of the necessary tunnel structures. Over almost 25 years the contractors relied on Herrenknecht’s project-specific tunneling technology for the underground excavation work in constructing sections 20, 30 and 40. This included numerous AVN machines for pipe jacking in the smaller diameter range, EPB Shields using the pipe jacking and segmental lining methods as well as a Vertical Shaft Sinking Machine (VSM) to sink a 23-m deep launch shaft.
RELATED: James W. Fowler Co.’s Use of Vertical Shaft Machine Marks U.S. First
Over 60 km of the main and secondary sections were built by contractors using Herrenknecht tunneling technology. In individual construction phases, Herrenknecht Group partners supported the quick overall construction process. VMT supplied TBM navigation systems as well as various communication, data management and safety systems. Herrenknecht Formwork produced segment molds and MSD supplied rolling stock, a lifting beam and a tilting table for the pipe plant in Gelsenkirchen.
The Emscher, whose source rises in Holzwickede to the east of Dortmund, passes through a series of cities in the German Ruhr area on its 80-km path before it flows into the Rhine. Since the beginning of industrialization around 1850, the small lowland river was used as an open channel for sewage, flood and rainwater and degenerated into the dirtiest river in Europe. With the renaturation of the stream, one of the main tasks of the Emschergenossenschaft founded in 1899, in future sewage and rainwater will be separated again, drained away underground and purified in intermediate treatment plants. As a result the river will become clean again in the long term and the quality of life of the people in the Ruhr area will increase. Commissioning of the 51-km long Emscher sewer is planned for the end of 2020.
RELATED: Herrenknecht TBM Constructs Large Road Tunnel in Switzerland
Comments are closed here.