Tunneling for National Grid’s Thames Crossing

Grain to Tilbury – the Mixshield is lifted into the launch shaft in Tilbury. (Photo: Herrenknecht)

Demand for electricity is expected to increase significantly and is forecast to double by 2050 as homes, businesses, public services, transport, and industry increasingly switch to electric power. National Grid’s Great Grid Upgrade is the largest overhaul of the electricity network in generations, helping to strengthen energy security by connecting more home-grown energy from more affordable sources.

Herrenknecht supplied the machinery for Grain to Tilbury, a key project in the grid upgrade. After a Herrenknecht Vertical Shaft Sinking Machine had excavated the launch shaft, tunneling began at the start of May on the 2,200-m long cable tunnel. On behalf of National Grid, the Ferrovial Bemo Joint Venture, consisting of Ferrovial Construction and BEMO Tunnelling UK Ltd., is constructing the tunnel for the 400 kV high-voltage cable.

Tunnel boring machine specifically tailored for the project

Herrenknecht AG has received an order from the Ferrovial Bemo JV for a tunnel boring machine (TBM) specifically tailored to the project’s requirements. The TBM of the Mixshield type has a diameter of 4,730 mm, is 108 m long, and weighs 464 tonnes in total. Beneath the Thames, the TBM is predicted to encounter a mixed ground of chalk and flintstones up to a compressive strength of 1000 MPa. Additionally, the high water pressure beneath the Thames poses a challenge. The construction site is located at the river’s mouth where it flows into the North Sea.

Accordingly, the TBM is designed to withstand a water pressure of 4.5 bar, partly due to the tidal range. While water and earth pressure prevail at the cutting face, the rest of the machine is maintained at atmospheric pressure. The highly sophisticated Mixshield, a technology developed by Herrenknecht, offers maximum tunneling safety thanks to precise tunnel face support. It is also sealed against water pressure 41 m below the Thames with a multiple sealing system. For work at the tunnel face, such as changing the cutting tools on the cutting wheel, the Mixshield features a personnel airlock that allows workers to gradually acclimate to the different pressure conditions – similar to a scuba dive.

Custom solutions and a comprehensive delivery package

The TBM not only excavates the tunnel but also lines it with precast concrete segments, known as lining segments. The tunnel will have an internal diameter of 4 m and an external diameter of 4.50 m. Using a hydraulic overcutter, the excavation diameter can be increased. This enables the machine to navigate curves and make course corrections more easily. The tunnel’s curve radius is 350 m.

Due to the complex geology, the Mixshield is designed including a Mini gripper and Anti-roll fins. This allows the machine to be secured so that the cutting wheel can be retracted if necessary. Additionally, the Mixshield is equipped with a drilling rig for preliminary exploration and a telescopic camera to inspect the tunnel face without hyperbaric interventions needed by the personnel. This allows obstacles in the ground to be detected in a timely manner and the necessary precautions to be taken.

The delivery package for the tunnel construction includes a separation plant, navigation technology from Herrenknecht’s subsidiary VMT and multi-service vehicles that transport the segments from the launch shaft to the TBM inside the tunnel.

Vertical Shaft Sinking Machine (VSM) during the construction of the launch shaft for the Thames Cable Tunnel. (Photo: National Grid)

Europe’s largest Vertical Shaft Sinking Machine excavates launch and target shaft

Europe’s largest Vertical Shaft Sinking Machine (VSM), with a diameter of 15,900 mm, is being used to construct the launch and reception shafts. The Herrenknecht VSM excavated the 45-m deep launch shaft in Tilbury on the north bank of the Thames in just four weeks, from mid-November to mid-December 2025. VSM technology is particularly well-suited for soft soils with high groundwater levels, as it does not require costly groundwater dewatering. By simultaneously driving the shaft wall and constructing the rings, driving speeds of up to 2.7 m per day have been achieved. This method shortens construction time, minimizes environmental impact, and increases safety, as no personnel are required in the shaft and all work is controlled entirely from the surface.

Herrenknecht is supplying a comprehensive equipment package for the shaft construction: in addition to the VSM, a high-performance separation plant for processing the excavated material and segment molds for ring construction. This is complemented by extensive services ranging from logistics to on-site support.

After the construction of the launch shaft in Tilbury, the VSM was dismantled and transported to the construction site of the receiving shaft in Gravesend. There, it has been constructing the receiving shaft – 48 m deep – from mid-March to the beginning of May. The tunnel boring machine will break through the shaft wall at a predefined, unreinforced location.

Share Article:

Comments are closed here.

TBM: Tunnel Business Magazine's Weekly Newsletter and More

Get industry news updates and product information to help you stay up to date.

By submitting this form, you acknowledge that we may use your personal information for marketing communications.