SR 99 Update: Bertha Completes 17 Rings

SR 99 TBMBertha, the SR 99 tunneling machine, has traveled approximately 110 feet since Seattle Tunnel Partners resumed mining on Feb. 23. The machine has tunneled a total of 1,391 feet and is approaching South Washington Street, according to WSDOT.

STP is now 17 concrete rings into the 25-ring demonstration period that was put in place when WSDOT conditionally lifted the Jan. 14 suspension for cause. Crews are mining north to a planned maintenance stop just south of Yesler Way. Once there, they could spend several weeks performing final maintenance before the machine tunnels beneath the Alaskan Way Viaduct.

RELATED: Northgate Link Project the Latest in Seattle’s Transit Build Out

Update on barging

While mining is ongoing, barging activities are still restricted pending submittal of additional documentation. STP is removing excavated soil by truck as they continue addressing the barging issue. Repairs to the pier that was damaged during the Jan. 12 barging incident were completed last month.

Share Article:

Comments are closed here.

TBM: Tunnel Business Magazine's Weekly Newsletter and More

Get industry news updates and product information to help you stay up to date.

By submitting this form, you acknowledge that we may use your personal information for marketing communications.