ACCIONA and Partners Complete River Diversion Tunnels for Site-C Project
Excavation of the diversion tunnels began in the summer of 2018 and was completed at the end of 2019. The process to line the tunnels, which used a custom-made slip form structure to ensure a perfect finish, began in the summer of 2019 and was completed this May.
The project commissioned to ACCIONA and its partner by BC Hydro involves the construction of an earthfill dam spanning more than 1 km that rises 60 m over the riverbed of the Peace River. The principal civil engineering contract also includes major auxiliary works such as construction of 5 km of cofferdams and the two recently completed river diversion tunnels, as well as various temporary access roads and bridges.
ACCIONA is also constructing an 800-m long to a maximum height of 70-m foundation structure from roller-compacted concrete (RCC) with a total volume of 1.8 million cubic meters, to support the hydroelectric power plant and the spillways.
Once completed, Site C will be the third hydroelectric dam and power plant on the Peace River and one of Canada’s largest dams. Once in operation, the project will provide 1,100 megawatts of capacity and about 5,100 gigawatt hours of energy each year to the province’s integrated electricity system. It will ensure the supply of clean and renewable energy for more than 100 years, to an average of 450,000 homes per year in BC.
For more information about the project, follow this link: https://www.sitecproject.com/
To find out more about the PRHP joint venture building the Site C Clean Energy Project, visit: http://www.prhp.ca/
Comments are closed here.